Construction Diary of Ambassador Golf Club Residence

Published:
18 October 2019

The roofing of the club house of the Ambassador Golf Club Residence is underway. By October 20, its full completion is planned. Installation of ventilation systems is 70% completed, and installation of heating and cooling systems is 90% complete. Electricity wiring is ongoing.

From October 21, work is resumed on the facade of the apartment complex, the installation of an individual heat point and the installation of an automatic fire extinguishing system.